In order to continuously improve our solutions, we will proceed to an important update of our IT infrastructure between the 12th and the 16th of August.

Please find the details below :


Object

Important update of our IT infrastructure

Begin

12th of August 2019

End

16th of August 2019

Description

  • Replacement of the central commutation (heart of network)
  • Replacement of 80% of blade servers
  • Replacement of two-thirds of blade frames
  • Reconfiguration of the firewall and the GRE tunnel

Estimated risk level

All our solutions could be impacted by this updates and may need to be shut down at some point. However, everything will be made to avoid any negative impact to the end user.